Phase 3B - Our Final Phase

Jul 28, 2021
Phase 3B public engagement
Qualico Communities has submitted three applications to the City of Winnipeg that will complete the final phase of RidgeWood West, Phase 3B.

The applications will create a total of 70 lots, comprised of 41 single-family lots with double-car attached garages, 17 single-family lots with single-car attached garages as well as, 12 duplex units with single-car attached garages.

Servicing is set to begin in late summer 2021 with completion this fall. With this timeline, potential lot release dates are late 2021/early 2022 depending on the application status and market demand.

Located in the southwest corner of the community, Phase 3B will also include a new public reserve space that is outlined as part of its applications. This will be the final piece in completing the naturalized trail system in RidgeWood West